BESS Battery project at Regina by SaskPower

Back in February I asked SaskPower how this project was going.

Our Progress So Far

In Fall of 2020, we engaged with neighbouring communities to discuss the proposed BESS plans. We’re now moving to the next phase of the project including project design and procurement. Other milestones include:

  • Infrastructure Canada conditional funding received: early 2021
  • Procure technology: mid 2021
  • Construction: late 2021
  • Energization: end of 2022

They replied today noting my email to their public enquiries address had been caught in their spam filter.

They’ve since updated the page as it’s behind schedule, but construction is now intended to begin this season.